Are They Going to Continue the Dakoto Pipeline Are They Going to Continue the Dakota Pipeline
Dakota Access Pipeline | |
---|---|
Location | |
Country | United States |
General direction | southeastward |
From | Stanley, North Dakota |
Passes through | States of North Dakota (Bismarck) South Dakota (Redfield, Sioux Falls) Iowa (Sioux Center, Storm Lake, Ames, Oskaloosa, Ottumwa, Fort Madison) Illinois (Jacksonville)[2] |
To | Patoka, Illinois (oil tank farm) |
General information | |
Type | Crude oil |
Partners | Energy Transfer Partners Phillips 66 Enbridge Marathon Petroleum |
Operator | Dakota Access Pipeline, LLC (development phase) Energy Transfer Partners (operational phase) |
Construction started | 2016 |
Commissioned | June 1, 2017 (2017-06-01) |
Technical information | |
Length | 1,172 mi (1,886 km) |
Maximum discharge | 0.47 million barrels per day (~2.3×10 |
Diameter | 30 in (762 mm) |
Website | daplpipelinefacts |
The Dakota Access Pipeline (DAPL) or Bakken pipeline is a 1,172-mile-long (1,886 km) underground pipeline in the United States that has the ability to transport up to 750,000 barrels of light sweet crude oil per day. It begins in the shale oil fields of the Bakken Formation in northwest North Dakota and continues through South Dakota and Iowa to an oil terminal near Patoka, Illinois. Together with the Energy Transfer Crude Oil Pipeline from Patoka to Nederland, Texas, it forms the Bakken system. The pipeline transports 40 percent of the oil produced in the Bakken region.
The $3.78 billion project was announced to the public in June 2014 with construction beginning in June 2016, creating approximately 42,000 jobs with a total of $2billion in wages. The pipeline was completed in April 2017 and became operational in May 2017. The pipeline is owned by Dakota Access, LLC, controlled by Energy Transfer Partners, with minority interests from Phillips 66, and affiliates of Enbridge and Marathon Petroleum.
Protests of the pipeline occurred organized by those opposing its construction, including the Standing Rock Indian Reservation.
History [edit]
Planning, 2014–2016 [edit]
Prior to the Dakota Access Pipeline, light sweet crude oil from the Bakken Formation was transported mainly by rail during the North Dakota oil boom.[4] [5] Extraction from the area increased from 309,000 barrels a day in 2010 to more than 1 million in 2014, with insufficient pipeline infrastructure to transport the increased extraction.[5] Plans for the pipeline were announced by Energy Transfer Partners in 2014,[6] with Phillips 66 acquired 25% stake in the project later that same year.[7] Energy Transfer Partners estimated that the pipeline would create between 12 and 15 permanent jobs and from 2,000 to 4,000 temporary jobs in Iowa. The $1.35 billion capital investment in Iowa was projected to generate $33 million sales tax in Iowa during construction and $30 million property tax in 2017.[8] Energy Transfer hired "Strategic Economics Group" in West Des Moines to prepare this analysis.[9] [10]
In September 2014, Dakota Access held an initial informational meeting with the Standing Rock Sioux Tribal Council. Informational meetings for South Dakota and Illinois landowners were held in October 2014,[8] and starting on December 1, 2014, in each of the affected counties in Iowa.[11] Meetings in Fort Madison, Sioux Center, Oskaloosa and Storm Lake brought out hundreds of people expressing their support and/or opposition to the pipeline.[12] [13] [14] [15] A webinar for Brown and Hancock County, Illinois took place in February 2015.[16]
On October 29, 2014, Dakota Access submitted the project to the Iowa Utilities Board (IUB),[17] after Iowa Governor Terry Branstad rejected requests from community and environmental activists who asked him to block plans.[18] In December 2014 Dakota Access submitted an application for a permit from the North Dakota Public Service Commission for the proposed route.[19] In January 2015, Dakota Access filed the application with the IUB.[20] In February 2015, it filed applications with the Iowa Department of Natural Resources for sovereign land and floodplain permits.[21] In April 2015, Iowa Senate Study Bill 1276 and House Study Bill 249 advanced with both Senator Robert Hogg, D-Cedar Rapids, and State Representative Bobby Kaufmann, R-Wilton, in support; it required Dakota Access "to obtain voluntary easements from 75% of property owners along the route before eminent domain could be authorized".[22]
The Iowa Utilities Board approved the pipeline on March 10, 2016, on a vote of 3 to 0, being the last of four states utility regulators granting its approval. The approval came after 18 public information meetings, pre-filled testimony, thousands of public comments, and 12 days of public hearings.[23] Conditions of the approval included liability insurance of at least $25 million; guarantees that the parent companies of Dakota Access will pay for damages created by a pipeline leak or spill; a revised agricultural impact mitigation plan; a timeline for construction notices; modified condemnation easement forms; and a statement accepting the terms and condition's of the board's order."[24] [25] The IUB stated that with the conditions, the pipeline would promote public convenience and necessity.[23] The following day, the company stated it had secured voluntary easements on 82% of the 1,295 affected Iowa land parcels.[26] A week later, Dakota Access filed motions with the IUB requesting expedited and confidential treatment to begin construction immediately, saying it met the conditions and that its liability insurance policies were trade secrets under Iowa law and "would serve no public purpose".[25] Dakota Access also filed 23 condemnation suits against 140 individuals, banks, and a coal mine to gain easements through North Dakota.[27]
A 2015 poll showed that fifty seven percents of Iowans favoring the construction of the pipeline.[28] Construction of the pipeline was also estimated to create 42,000 jobs with a total of $2billion in wages.[29]
Construction, 2016–2017 [edit]
In March 2016, the United States Fish and Wildlife Service issued a sovereign lands construction permit. In late May 2016, the permit was temporarily revoked in three counties of Iowa, where the pipeline would cross the Big Sioux River and the Big Sioux Wildlife Management Area; these are historic and cultural sites of the Upper Sioux tribe, including graves in Lyon County.[30] Also in May 2016, Iowa farmers filed lawsuits to prevent the state from using eminent domain.[31]
In June 2016, the IUB voted 2 to 1 (Libby Jacobs and Nick Wagner in favor and Chairwoman Geri Huser against) to allow construction on non-sovereign lands to continue. The Sierra Club said this action was illegal before the US Corps of Engineers authorized the project.[32] In late June 2016, construction was allowed to resume in Lyon County after plans were changed to route the pipeline 85 feet (26 m) below the site using directional boring, instead of trenching and disturbing the soil on the surface.[33] In December 2016, the approval was disputed in the Polk County District Court.[34] In July and August 2016, The United States Army Corps of Engineers (USACE) approved the water crossing permits and issued all but one permission necessary for the pipeline construction.[35] [36]
On July 27, 2016, the Standing Rock Sioux Tribe sued the USACE in the United States District Court for the District of Columbia.[37] [38] [39] The motion for preliminary injuction was denied in the U.S. District Court in September 2016. In September 2016, the Standing Rock Sioux Tribe filed an appeal which was denied a month later.[40]
In August 2016, the joint venture of Enbridge (75%) and Marathon Petroleum (25%) agreed to purchase a 49% stake in Dakota Access, LLC for $2 billion.[41] [42] The deal was completed in February 2017 after the final easement was granted.[43]
In September 2016 the U.S Department of Justice received more than 33,000 petitions to review all permits and order a full review of the project's environmental effects.[44] On September 9, 2016, the US Departments of Justice, Army, and Interior issued a joint statement to temporarily halt the project on federal land bordering or under the Lake Oahe reservoir. The US federal government asked the company for a "voluntary pause" on construction near the area until further study was done in the region extending 20 miles (32 km) around Lake Oahe.[39] [45] Energy Transfer Partners rejected the request and resumed construction.[46] On September 13, 2016, chairman and CEO of Energy Transfer Partners Kelcy Warren said concerns about the pipeline's impact on the water supply were "unfounded", that "multiple archaeological studies conducted with state historic preservation offices found no sacred items along the route" and that the company would meet with officials in Washington "to understand their position and reiterate our commitment to bring the Dakota Access Pipeline into operation."[47]
On November 1, 2016, President Obama announced his administration was monitoring the situation and had been in contact with the USACE to examine the possibility of rerouting the pipeline to avoid lands that Native Americans hold sacred.[48] On November 14, 2016, the USACE announced that "the Army has determined that additional discussion and analysis are warranted in light of the history of the Great Sioux Nation's dispossessions of lands, the importance of Lake Oahe to the Tribe, our government-to-government relationship, and the statute governing easements through government property."[49] Energy Transfer Partners responded by criticizing the Obama administration for "political interference" and said that "further delay in the consideration of this case would add millions of dollars more each month in costs which cannot be recovered." North Dakota Governor Jack Dalrymple criticized the decision saying the pipeline would be safe and that the decision was "long overdue".[50] Craig Stevens, spokesman for the Midwest Alliance for Infrastructure Now (MAIN) Coalition, called the Corps's announcement "yet another attempt at death by delay" and said the Obama administration "has chosen to further fan the flames of protest by more inaction." North Dakota Senator John Hoeven said in a statement that the delay "will only prolong the disruption in the region caused by protests and make life difficult for everyone who lives and works in the area."[51] Speaking to CBS News in November, Kelcy Warren said that it would be "100 percent that the easement gets granted and the pipeline gets built" when newly elected president elect Donald Trump came into office on January 20, 2017.[52]
On December 4, 2016, the USACE announced, it would not grant an easement for the pipeline to be drilled under Lake Oahe and was undertaking an environmental impact statement to look at possible alternative routes.[53] [54] [55] The Assistant Secretary of the Army (Civil Works), Jo-Ellen Darcy said that "the best way to complete that work responsibly and expeditiously is to explore alternate routes for the pipeline crossing".[56] Energy Transfer Partners and Sunoco Logistics Partners issued a same-day response saying that the White House's directive "is just the latest in a series of overt and transparent political actions by an administration which has abandoned the rule of law in favor of currying favor with a narrow and extreme political constituency." They said that the companies "fully expect to complete construction of the pipeline without any additional rerouting in and around Lake Oahe. Nothing this Administration has done today changes that in any way."[57]
On January 18, 2017, the USACE filed its formal Notice of Intent to conduct the Environmental Impact Statement process.[58] The notice opened a thirty-day comment on the scope of the EIS, addressing the crossing of Lake Oahe. The proposed EIS was to consider "Alternative locations for the pipeline crossing the Missouri River", direct and indirect risks and impacts, as well as their treaty rights to the lake.[58] The same day U.S. District Judge James Boasberg denied ETP's request to delay the EIS process.[59]
Following the inauguration of Donald Trump in January 2017, he signed a presidential memorandum to advance approval of pipeline construction, while stating his intention to "renegotiate some of the terms" of the pipeline bill.[60] The order would expedite the environmental review that Trump described as an "incredibly cumbersome, long, horrible permitting process."[61] [62] These executive orders, which also included the Keystone XL Pipeline, outlined how the completion of the pipeline would create more jobs.[63]
On February 7, 2017, the USACE sent a notice of intent to the United States Congress to grant an easement under Lake Oahe 24 hours following notification of the delivery of the notification.[64] [65] On February 9, 2017, the Cheyenne River Sioux sued the easement decision, citing an 1851 treaty and interference with the religious practices of the tribe.[66] [67] [68]
The Dakota Access Pipeline had temporary workforce housing for the pipeline workers.[69] Construction of the pipeline was completed in April 2017.[70]
Operation, 2017 to present [edit]
The first oil was delivered through the pipeline on May 14, 2017.[70] On June 1, 2017, testing was completed and the pipeline became commercially operational.[71] [72]
After the pipeline's first year of operation, Forbes reported that it was transporting over 500,000 barrels per day (79,000 m3/d) and had transported approximately 182.5 million barrels (29.02×10 ^ 6 m3) of oil.[73] By 2021, the pipeline had the ability to transport 750,000 barrels of oil per day[74] and was accounting for 40 percent of oil produced in the Bakken region.[75]
A United States District Judge James E. Boasberg, appointed by President Barack Obama, ruled in March 2020 that the government had not studied the pipeline's "effects on the quality of the human environment" enough, ordering the United States Army Corps of Engineers to conduct a new environmental impact review.[76] In July 2020, Judge Boasberg ordered the pipeline to be shut down and emptied of oil pending a new environmental review.[77] [78] The temporary shutdown order was overturned by a U.S. appeals court on August 5, though the environmental review is expected to continue.[79]
Technical description [edit]
The pipeline cost $3.78 billion, of which $1.4 billion was invested in the North Dakota portion, $820 million was invested in the South Dakota portion, $1.04 billion was invested in the Iowa portion, and $516 million was invested in the Illinois portion.[80]
The pipeline has a permanent easement of 50 feet (15 m) and a construction right-of-way of up to 150 feet (46 m). The 30-inch (760 mm) diameter pipeline is at least 48 inches (1.2 m) underground from the top of the pipe or 2 feet (0.61 m) below any drain tiles.[81] At the length of 1,172 miles (1,886 km) and diameter of 30 inches (760 mm), the entire pipeline volume is 30,214,400 cubic feet (855,576 m3). At the stated daily transport volume of 2,600,000 cubic feet (75,000 m3), the discharge time to empty the whole pipeline is estimated at 11.4 days.[82]
Capacity expansion construction was undertaken by Energy Transfer Partners in 2021, which increased the line's capacity from 570,000 bpd to its current nameplate of 750,000.[83]
Comparison to rail transport [edit]
The developer argued that the pipeline improves the overall safety to the public, would help the US to attain energy independence, and is a more reliable and safer method of transport to refineries than rail or road. Proponents have argued that the pipeline will free up railroads, which will allow farmers to ship more Midwest grain.[84] As of July 2014[update], Bakken shale oil was transported through nine Iowa counties exclusively via three freight trains per week.[85] As of June 2014, 32 trains per week carrying Bakken oil traveled through Jo Daviess County in northwestern Illinois.[86]
Ownership [edit]
The pipeline is owned by Energy Transfer (36.4% stake), MarEn Bakken Company LLC, and Phillips 66 Partners. MarEn Bakken Company LLC is an entity owned by MPLX LP (an affiliate of Marathon Petroleum) and Enbridge Energy Partners L.P.[87]
Bakken Holdings Company and Phillips 66 also co-own another part of the Bakken system, the Energy Transfer Crude Oil Pipeline which runs from Patoka to storage terminals in Nederland, Texas.[7] [87]
Financing [edit]
The pipeline project cost $3.78 billion, of which $2.5 billion was financed by loans, while the rest of the capital was raised by the sale of ownership in Dakota Access, LLC to Enbridge and Marathon Petroleum.[88] The loans were provided by a group of 17 banks, including Citibank, Wells Fargo, BNP Paribas, SunTrust, Royal Bank of Scotland, Bank of Tokyo-Mitsubishi, Mizuho Bank, TD Securities, ABN AMRO Capital, ING Bank, DNB ASA, ICBC, SMBC Nikko Securities and Société Générale.[89]
Due to pressure resulting from the Dakota Access Pipeline protests, some banks decided to pull funding in the project. This included DNB ASA Financial services group.[90] [91] In February 2017, Seattle, Washington's city council unanimously voted not to renew its contract with Wells Fargo "in a move that cites the bank's role as a lender to the Dakota Access Pipeline project as well as its "creation of millions of bogus accounts" and saying the bidding process for its next banking partner will involve "social responsibility." The City Council in Davis, California, took a similar action, voting unanimously to find a new bank to handle its accounts by the end of 2017.[92] In March 2017, ING sold its stake in the loan, while retaining a potential risk in case of non-payment under the loan.[93] [94]
Thirteen of the 17 banks that financed the pipeline were signatories to the Equator Principles. Despite concerns being raised that the project could threaten the water supply from Lake Oahe and the Missouri River if a leak occurred, project financing was still approved.[95] [96]
Route [edit]
The pipeline route runs from the northwestern North Dakota Bakken and Three Forks sites. It starts in Stanley, North Dakota, and travels in a southeastward direction to end at the oil tank farm near Patoka, Illinois.[7] It crosses 50 counties in four states,[97] and is built on private land with portions crossing waters of the United States and flood control areas managed by the United States Army Corps of Engineers.[98]
In North Dakota, the 346-mile (557 km) route traverses seven counties.[80] The project consists of 143 miles (230 km) of oil-gathering pipelines and 200 miles (322 km) of larger transmission pipeline. The route starts with a terminal in the Stanley area and runs west with five more terminals in Ramberg Station, Epping, Trenton, Watford City and Johnsons Corner before becoming a transmission line going through Williston, the Watford City area, south of Bismarck, and crossing the Missouri River again north of Cannon Ball.[99] It also includes six tank farm locations and one electric pump station.[80]
In the early stages of route planning, it was proposed laying the pipeline 10 miles (16 km) northeast of Bismarck, North Dakota.[100] [101] The United States Army Corps of Engineers (USACE) evaluated alternative routes as part of compliance with the National Environmental Policy Act, including one route north of Bismarck, North Dakota. This alternative was determined not to be a viable alternative because of multiple factors, including that it was not co-located with other infrastructure, the route's impacts to wellhead water resources, constraints on the route from the North Dakota Public Service Commission's 500-foot residential buffer requirement and the route's additional impacts to areas identified as High Consequence areas under Pipeline and Hazardous Materials Safety Administration regulations.[102]
The Bismarck route was rejected by the United States Army Corps of Engineers (USACE) before submitting a request to the North Dakota Public Service Commission (NDPSC) for a permit.[101] [103] This decision was described by Jesse Jackson as environmental racism.[103] The change of the route put the pipeline into the existing pipeline corridor parallel to the already existing Northern Border Pipeline, a natural gas pipeline built in 1982.[103] [104] The Dakota Access pipeline selected a "nearly identical route" and planned to cross the Missouri River near the same point.[104] The plans called for the pipeline to be directionally bored so that it would not come in contact with the Missouri River. It is planned to be "as deep as 90 feet (27.4 m)" below the riverbed.[105] [106]
In South Dakota, the pipeline travels 274 miles (441 km) through 12 counties: Campbell, McPherson, Edmunds, Faulk and Spink.[107] The system includes one electric pump station.[80]
In Iowa, the pipeline extends about 347 miles (558 km) diagonally through 18 Iowa counties: Lyon, Sioux, O'Brien, Cherokee, Buena Vista Sac, Calhoun, Webster, Boone, Story (which will have a pumping station), Polk, Jasper, Mahaska Keokuk, Wapello, Jefferson, Van Buren, and Lee.[108] [109] The system includes one electric pump station.[80]
In Illinois, the 177-mile (285 km) route traverses 12 counties.[80]
Federal agencies permissions [edit]
Most of the pipeline was built with permits issued under state law. Federal jurisdiction arises through the United States Army Corps of Engineers for 37 miles of the pipeline where it passes over or under streams, rivers, and federal dams.[110] The USACE has conducted a limited review of the route, involving an environmental assessment of river crossings and portions of the project related to specific permits, and issued a finding of no significant impact. It did not carry out an area-wide full environmental impact assessment of the entire effects of the overall project through the four states.[111] The USACE was authorized to grant the following:
- verification of Nationwide Permit #12 permits for 202 crossings of jurisdictional waters under Section 10 of the Rivers and Harbors Act and Section 404 of the Clean Water Act;
- permissions for consent to cross flowage easements acquired and administered by USACE at Lake Sakakawea and Carlyle Reservoir, under Section 14 of the Rivers and Harbors Act of 1899, codified 33 U.S.C. Section 408 (Section 408)
- permissions to modify the Oahe Dam/Lake Oahe project by granting easements to cross federal property administered by USACE for the flood control and navigation project, under Section 408;
- permissions to cross the McGee Creek Levee, the Illinois River navigation channel and the Coon Run Levees, under Section 408;
- permission to horizontally directionally drill under the Mississippi River navigation channel, under Section 408.[35]
On June 14, 2017, a federal judge ordered the federal government to conduct further reviews of the pipeline but did not halt pumping operations.[112] On March 25, 2020, a U.S. District judge ordered the U.S. Army Corps of Engineers to conduct a full environmental review.[113]
Concerns [edit]
Health and environment [edit]
Conservation groups raised concerns about safety, and the impacts on air, water, wildlife and farming, because of the risk of the pipeline disruption.[114] Groups such as Greenpeace, the Science & Environmental Health Network,[115] and a group of more than 160 scientists spoke out against the pipeline.[116] [117] [118]
Environmentalists and Native Americans expressed concerns the Missouri River might become contaminated in the event of a spill or leak.[116] [119]
Prior to construction, some farmers expressed concern about the disturbance of the land, including tiling, soil erosion, and soil quality.[14] They also expressed concerns about potential leaks in the pipeline caused by destabilization in certain areas prone to flooding, which could cause an environmental disaster,[120] as well as the spread of invasive weeds into surrounding land.[121]
Eminent domain [edit]
Landowners across Iowa expressed concern about allowing the use eminent domain to condemn privately owned land, particularly agricultural land.[84] In March 2015, a Des Moines Register poll found that while 57% of Iowans supported the Dakota Access Pipeline, 74% were opposed to the use of eminent domain condemnation on behalf of a private corporation.[28]
In August 2016, the company stated that it had already executed easement agreements with 99% of the landowners whose properties lie along the four-state route and, with regards to the landowners along the pipeline's route in Iowa, 99% had entered voluntary easements.[122]
Tribal positions [edit]
The pipeline was opposed by the Standing Rock Sioux and the Cheyenne River Sioux tribes,[123] despite it not crossing tribal lands.[124] In September 2014, Standing Rock Chairman Dave Archambault II indicated the tribe's opposition to any pipeline within treaty boundaries encompassing "North Dakota, Montana, Wyoming and South Dakota."[3] The tribe contended that the route would run across sacred sites and be a potential hazard to its water supply.[125] Dakota Access stated the route was chosen based on it running alongside existing infrastructure including railways and other pipelines.[125]
The Mandan, Hidatsa, and Arikara Nation (known as the Three Affiliated Tribes) originally supported the Standing Rock Sioux tribe in its protest of the pipeline.[126] The tribe later argued against shutting down the pipeline, citing significant financial harm to the tribe who uses the pipeline to transport 60 percent of oil produced on its land.[127]
The Meskwaki tribe opposed the pipeline citing concerns that the pipeline could be used as a replacement if the Keystone XL pipeline is not built.[128]
Saying that "the Corps effectively wrote off the tribe's concerns and ignored the pipeline's impacts to sacred sites and culturally important landscapes," the Standing Rock Sioux Tribe has sued the USACE in the United States District Court for the District of Columbia, accusing the agency of violating the National Historic Preservation Act and other laws, and seeking declaratory and injunctive relief to stop the pipeline.[37] [38] [39] [129] This claim was rejected by the court. U.S. District Judge James E. Boasberg said in the ruling that the USACE "likely complied" with its obligation to consult the tribe and that the tribe "has not shown it will suffer injury that would be prevented by any injunction the Court could issue."[130]
On September 20, 2016, Dave Archambault II addressed the UN Human Rights Council in Geneva, Switzerland, where he called "upon all parties to stop the construction of the Dakota Access Pipeline." Citing the 1851 Treaty of Traverse des Sioux and 1868 Treaty of Fort Laramie, two treaties ratified by the U.S. Senate that recognize the Sioux's national sovereignty, Archambault told the Council that "the oil companies and the government of the United States have failed to respect our sovereign rights."[131] On September 22, 2016, Victoria Tauli-Corpuz, a United Nations expert on the rights of indigenous peoples, admonished the U.S., saying, "The tribe was denied access to information and excluded from consultations at the planning stage of the project, and environmental assessments failed to disclose the presence and proximity of the Standing Rock Sioux Reservation." She also responded to the rights of pipeline protesters, saying, "The U.S. authorities should fully protect and facilitate the right to freedom of peaceful assembly of indigenous peoples, which plays a key role in empowering their ability to claim other rights."[132] According to the USACE's data there had been 389 meetings with more than 55 tribes, including nine meetings with The Standing Rock Sioux Tribe.[133] Kelcy Warren has stated that the company is not on any Native American property.[134]
In December 2016, Trump's Native American Coalition held a meeting where members, American Indian and Alaska Native Tribal leaders, and activists could be present to discuss a wide variety of topics that concerned the effects and implications of the pipeline construction as well as environmental protections and safety concerns.[135]
Archaeological surveys [edit]
Several groups, including the Standing Rock Sioux and the Society for American Archaeology, have raised concerns over the thoroughness of archaeological surveys conducted along the pipeline's corridor. These surveys were carried out under the direction of the USACE, in compliance with the National Historic Preservation Act (NHPA).[136] The NHPA requires consideration of archaeological sites and traditional cultural properties.[137] [138] The initial survey showed 149 sites and the pipeline was subsequently moved to avoid 140 of them.[139] [140] The Advisory Council on Historic Preservation, which oversees compliance with the NHPA, raised two primary concerns to the USACE about the surveys.[136] [141] They criticized the scope of the investigation, which defined each water crossing as a separate project, and therefore failed to consider the pipeline as a whole.[136] [141] They also criticized the lack of tribal involvement in the surveys.[136] [141]
Tribal consultants help archaeologists identify sites that may be harder to see within the archaeological record, such as traditional cultural properties.[139] A traditional cultural property is a property whose "significance derived from the role the property plays in a community's historically rooted beliefs, customs, and practices."[137] The USACE reached out to the Standing Rock Sioux on several occasions for consultation, but were denied.[139] The Sioux refused to participate unless they could consult on the whole pipeline.[139] One instance of tribal consultation at Lake Oahe pointed out several cultural sites and a cemetery that the USACE were previously unaware of.[139]
On September 2, 2016, Tim Mentz, a former historic preservation officer for the Standing Rock Sioux, testified in DC District Court that 27 graves and 82 sacred sites were to be disturbed by the Cannonball river section of the pipeline.[139] [142] That weekend this area was bulldozed.[139] [142] [143] [144] On September 21, 2016, 1,281 anthropologists, archaeologists, museum officials, and others signed and released a letter in support of the tribal community, calling for further study of the area to be affected by the pipeline in South Dakota.[145] The Society for American Archaeologists also sent a letter to the USACE, detailing their organizations concerns over the project.[145] [146]
According to the North Dakota State Historic Preservation Office, the areas highlighted by Tim Mentz were evaluated by state officials on both September 21 and October 20, 2016.[139] They found that only four stone features would be directly impacted by the pipeline.[139] However, many are still concerned about the cumulative effect the project may have on sites that lie outside the 150 ft corridor.[139] [141] Jon Eagle, a Historic Preservation Officer for the tribe, was invited to participate in the evaluation on Sept. 23, but was not allowed access to the areas of the corridor on private property.[144] The tribe insists that evidence was destroyed by the construction company, as grading had gone on in the area previously.[139] [142] [143] [144]
Political ties [edit]
According to his federal disclosure forms, filed in May 2016, President Donald Trump held between $15,000 and $50,000 in stock in Energy Transfer Partners – down from $500,000 to $1 million in 2015 – and between $100,000 and $250,000 in Phillips 66. The Washington Post reported that Trump sold off his shares in Energy Transfer Partners in the summer of 2016.[147] The senior Democrat on the Public Resources Committee, Raul Grijalva, called this appearance of conflict of interest "disturbing". [148]
Energy Transfer Partners CEO Kelcy Warren contributed $6 million to the Rick Perry 2016 presidential campaign,[149] as well as $103,000 to the Donald Trump 2016 presidential campaign.[150] [151]
Protests [edit]
Many Sioux tribes have said that the pipeline threatens the Tribe's environmental and economic well-being, and that it has damaged and destroyed sites of great historic, religious, and cultural significance. The tribe has expressed concern over leaks because the pipeline passes under Lake Oahe, which serves as a major source of water.[152] Protests at pipeline construction sites in North Dakota began in the spring of 2016 and drew indigenous people, calling themselves water protectors and land defenders,[153] from throughout North America as well as many other supporters, creating the largest gathering of Native Americans in the past hundred years.[154]
In April 2016, a Standing Rock Sioux elder established a camp near the Missouri River at the site of Sacred Stone Camp, located within the Standing Rock Indian Reservation, as a center for cultural preservation and spiritual resistance to the pipeline, and over the summer the camp grew to thousands of people.[155] In July, ReZpect Our Water, a group of Native American youth, ran from Standing Rock in North Dakota to Washington, DC to raise awareness of what they perceive as a threat to their people's drinking water and that of everyone who relies on the Missouri and Mississippi rivers for drinking water and irrigation.[81] [129]
While the protests drew international attention and were said to be "reshaping the national conversation for any environmental project that would cross the Native American land",[156] there was limited mainstream media coverage of the events in the United States until early September.[157] At that time, construction workers bulldozed a section of land that tribal historic preservation officers had documented as a historic, sacred site, and when protesters entered the area security workers used attack dogs, which bit at least five of the protesters. The incident was filmed and viewed by several million people on YouTube and other social media.[158] [159] [160] [161] In late October, armed soldiers and police with riot gear and military equipment cleared an encampment that was directly in the proposed pipeline's path.[162] [163]
According to state and federal authorities, there were several cases of arson that damaged pipeline construction equipment in Iowa during 2016. One deliberately set fire caused nearly $1 million in damage to construction equipment in August in Jasper County, Iowa. Two other fires involving pipeline construction equipment were set around the same time in the same county and another was set in Mahaska County.[164] In October, another arson fire caused $2 million worth of damage to pipeline construction equipment in Jasper County, Iowa.[165]
See also [edit]
- List of natural gas pipelines in North America
- List of oil pipelines in North America
- List of pipeline accidents
- List of oil refineries in North America
References [edit]
- ^ "Bakken Pipeline Map". bakkenpipelinemap.com. n.d. Retrieved December 14, 2016.
- ^ Petroski, William (March 16, 2015). "Meskwaki tribe opposes Bakken oil pipeline through Iowa". USA Today . Retrieved April 8, 2015.
- ^ a b Sept 30th DAPL meeting with SRST. Standing Rock Sioux Tribe. September 30, 2014. Event occurs at 5:48. Retrieved November 27, 2016 – via Youtube.
(evocation of treaty boundaries: Fort Laramie Treaties (1851 and 1868) and standing resolution from 2012). Afterward, Chuck Frey (VP of ETP) makes a presentation of the DAPL project.
- ^ "Dakota Access Pipeline". US Army Corps of Engineers. Retrieved June 23, 2022.
- ^ a b Saha, Devashree (September 14, 2016). "Five things to know about the North Dakota Access Pipeline debate". Brookings. Retrieved June 13, 2022.
- ^ Worland, Justin (September 10, 2016). "The Fight Over the Dakota Access Pipeline Could Be the Next Keystone". Time. Retrieved June 13, 2022.
- ^ a b c Aronsen, Gavin (October 28, 2014). "Energy Transfer, Phillips 66 partner on Iowa pipeline". Ames Tribune.
- ^ a b Keenan, Chelsea (October 1, 2014). "Texas energy company releases more details on pipeline". The Gazette.
- ^ Eller, Donnelle (November 12, 2014). "Pipeline could bring $1.1 billion to Iowa". Des Moines Register.
- ^ Eller, Donnelle (December 4, 2014). "Unlikely allies join to fight pipeline project". Iowa City Press-Citizen.
- ^ Boshart, Rod (December 1, 2014). "Iowa oil pipeline meetings start today". The Gazette.
- ^ Joyce Russell (December 2, 2014). "Landowners Question Bakken Pipeline". Iowa Public Radio. NPR.org. Retrieved December 3, 2014.
- ^ "Concerns voiced at oil pipeline meeting in S.E. Iowa". Associated Press. December 1, 2014.
- ^ a b Krause, Rachael (December 1, 2014). "Hundreds Pack Inside Sioux Center Meeting On Proposed Dakota Access Pipeline Project". SiouxLandMatters.com. Nexstar Broadcasting, Inc. Retrieved December 4, 2014.
- ^ Mark Tauscheck (December 3, 2014). "Iowans pack meeting on new oil pipeline". KCCI-TV. Des Moines Hearst Television Inc. Retrieved December 4, 2014.
- ^ "Two county Farm Bureaus to host crude oil pipeline webinar". Illinois Farm Bureau. February 6, 2015. Retrieved March 3, 2015.
- ^ Iowa Utilities Board (n.d.). "Docket Summary for Docket HLP-2014-0001". Retrieved December 1, 2014.
- ^ Petroski, William (October 14, 2014). "Branstad won't stop Bakken oil pipeline through Iowa". Des Moines Register . Retrieved December 1, 2014.
- ^ Dakota Access, LLC (December 2014). "North Dakota Public Service Commission Combined Application for Certificate of Corridor Compatibility and Route Permit" (PDF).
- ^ Petroski, William (January 20, 2015). "Bakken pipeline OK requested; setting up Iowa showdown". Des Moines Register . Retrieved February 10, 2015.
- ^ Lloyd, John (February 7, 2015). "Proposed Bakken pipeline construction requires at least two DNR permits". Boone News–Republican . Retrieved December 14, 2016.
- ^ Petroski, William (April 28, 2015). "Iowa bills place hurdles for Bakken pipeline, powerline". Des Moines Regicter . Retrieved May 1, 2015.
- ^ a b "Iowa Utilities Board approves Dakota Access pipeline permit with landowner protections" (PDF). Iowa Utilities Board. March 10, 2016. Retrieved June 13, 2022.
- ^ Kim St. Onge IUB announces decision on oil pipeline KCCI, March 9, 2016
- ^ a b William Petroski, Bakken pipeline firm seeks expedited construction permit Des Moines Register, March 17, 2016
- ^ William Petroski Bakken pipeline secures 82 percent of Iowa land parcels Des Moines Register, March 11, 2016
- ^ Donovan, Lauren (January 4, 2016). "Dakota Access still seeking 23 condemnation suits for pipeline easements". AG Week. Retrieved June 13, 2022.
- ^ a b "Iowa Poll: Iowans back energy projects, but oppose eminent domain". Des Moines Register. March 2, 2015. Retrieved March 2, 2015.
- ^ marsh, Rene (January 28, 2017). "Keystone pipeline: How many jobs it would really create". CNN. Retrieved June 22, 2022.
- ^ Petrowski, William (May 27, 2016). "Tribal land issues block Bakken pipeline in Iowa". Des Moines Register . Retrieved June 8, 2016.
- ^ Petroski, William (May 20, 2016). "Iowa farmers sue to block use of eminent domain for Bakken pipeline". Des Moines Register . Retrieved July 23, 2016.
- ^ William Petrowski (June 6, 2016). "Despite critics, Bakken pipeline gets go-ahead in Iowa". Des Moines Register . Retrieved June 8, 2016.
- ^ Petroski, William (June 20, 2016). "Bakken pipeline will run under sacred tribal site". Des Moines Register . Retrieved November 26, 2016.
- ^ Petroski, William (December 15, 2016). "Dakota Access pipeline approval disputed in Iowa court". Des Moines Register . Retrieved January 8, 2017.
- ^ a b "Frequently Asked Questions DAPL". US Army Corps of Engineers. Retrieved January 12, 2017. This article incorporates text from this source, which is in the public domain.
- ^ Moyers, Bill (September 9, 2016). "What You Need to Know About the Dakota Access Pipeline Protest". Common Dreams. Retrieved October 26, 2016.
- ^ a b "Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers. Complaint for Declaratory and Injunctive Relief" (PDF). In the United States District Court for the District of Columbia (1:16-cv-01534-Document 1). July 27, 2016. Retrieved August 6, 2016.
- ^ a b "Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers. Memorandum in Support of Motion for Preliminary Injunction Expedited Hearing Requested" (PDF) (1:16-cv-1534-JEB). United States District Court for the District of Columbia. August 4, 2016. Archived from the original (PDF) on August 7, 2016. Retrieved August 6, 2016.
- ^ a b c Monet, Jenni (September 10, 2016). "Standing Rock Sioux tribe claims small victory in pipeline battle". pbs.org. Retrieved September 17, 2016.
- ^ Delfeus, Sophie (December 19, 2016). "The suspended battle at Standing Rock". Intercontinental Cry . Retrieved January 8, 2017.
- ^ Cryderman, Kelly (August 2, 2016). "Enbridge, Marathon Petroleum buy Bakken pipeline stake for $2-billion". The Globe and Mail . Retrieved November 6, 2016.
- ^ Penty, Rebecca (August 3, 2016). "Enbridge, Marathon Agree to Buy $2 Billion Bakken Pipe Stake". Bloomberg. Retrieved November 6, 2016.
- ^ Johnson, Brooks (February 15, 2017). "Enbridge closes on Dakota Access stake". Duluth News Tribune . Retrieved April 29, 2017.
- ^ Michael Leland, Iowa Public Radio (September 15, 2016). "Bakken pipeline opposition presents petitions to U.S. Justice Department". Radio Iowa. Retrieved September 25, 2016.
- ^ "Joint Statement from the Department of Justice, the Department of the Army and the Department of the Interior Regarding Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers". Office of Public Affairs, United States Department of Justice. September 9, 2016. Retrieved September 17, 2016.
- ^ Medina, Daniel A. (November 4, 2016). "Dakota Access Pipeline: What's Behind the Protests?". NBC News . Retrieved November 5, 2016.
- ^ Gaudiano, Nicole (September 13, 2016). "Bernie Sanders, Native Americans say oil pipeline will poison drinking water". USA Today.
- ^ Hersher, Rebecca. "Obama: Army Corps Examining Possible Rerouting Of Dakota Access Pipeline". National Public Radio. Retrieved December 1, 2016.
- ^ "Corps: More discussion needed before agency will approve Dakota Access easement". The Bemidji Pioneer. Archived from the original on November 29, 2016. Retrieved December 13, 2016.
- ^ MacPherson, James; Nicholson, Blake (November 15, 2016). "Pipeline Company Seeks Court Permission to Proceed With Plan". ABC news . Retrieved November 18, 2016.
- ^ "Corps: More discussion needed before agency will approve Dakota Access easement". The Bemidji Pioneer. Bemidji Pioneer and Forum Communications Company. November 14, 2016. Archived from the original on November 29, 2016. Retrieved November 18, 2016.
- ^ "A Violation of Tribal & Human Rights: Standing Rock Chair Slams Approval of Dakota Access Pipeline". Democracy Now. February 8, 2017.
- ^ "Standing Rock Sioux Tribe's Statement on U.S. Army Corps of Engineers Decision to Not Grant Easement" (Press release). Stand With Standing Rock. December 4, 2016. Archived from the original on December 4, 2016. Retrieved December 4, 2016.
- ^ "Dakota Access Pipeline to be rerouted". CNN. December 4, 2016. Retrieved December 4, 2016.
- ^ Healy, Jack; Fandos, Nicholas (December 5, 2016). "Protesters Gain Victory in Fight Over Dakota Access Oil Pipeline". The New York Times. p. A1. Retrieved December 5, 2016.
- ^ "Army will not grant easement for Dakota Access Pipeline crossing" (Press release). U.S. Army ASA (CW). December 4, 2016. Archived from the original on December 4, 2016. Retrieved December 5, 2016.
- ^ "Energy Transfer Partners and Sunoco Logistics Partners Respond to the Statement from the Department of the Army" (Press release). Energy Transfer Partners. December 4, 2016. Retrieved December 14, 2016 – via Business Wire.
- ^ a b "Notice of Intent To Prepare an Environmental Impact Statement in Connection With Dakota Access, LLC's Request for an Easement To Cross Lake Oahe, North Dakota". Federal Register. January 18, 2017. Retrieved January 24, 2017.
- ^ "Federal Study on Dakota Access Pipeline to Move Forward". ABC News. Archived from the original on January 24, 2017. Retrieved January 24, 2017.
- ^ Jones, Athena; Diamond, Jeremy; Krieg, Gregory (January 24, 2017). "Trump advances controversial oil pipelines with executive action". CNN. Retrieved April 29, 2017.
- ^ Mufson, Steven (January 24, 2017). "Trump seeks to revive Dakota Access, Keystone XL oil pipelines". The Washington Post. Washington, DC. Retrieved January 24, 2017.
- ^ Jacobs, Jennifer; Dlouhy, Jennifer A.; Vamburkar, Meenal (January 24, 2017). "Trump Pins Keystone and Dakota Pipeline Fate on Renegotiation". Bloomberg. Retrieved January 24, 2017.
- ^ "Executive Order Expediting Environmental Reviews and Approvals For High Priority Infrastructure Projects". whitehouse.gov (Press release). January 24, 2017. Retrieved April 29, 2017 – via National Archives.
- ^ Hersher, Rebecca (February 7, 2017). "Army Approves Dakota Access Pipeline Route, Paving Way For The Project's Completion". NPR. Retrieved February 8, 2017.
- ^ "Dakota Access Pipeline Notification Grijalva". Retrieved February 8, 2017.
- ^ Winsor, Morgan; Hill, James (February 9, 2017). "Cheyenne River Sioux Tribe Files 1st Legal Challenge Over Dakota Access Pipeline Easement". ABC News . Retrieved February 10, 2017.
- ^ Chappell, Bill (February 9, 2017). "Tribe Reportedly Files Legal Challenge To Dakota Access Pipeline". NPR . Retrieved February 24, 2017.
- ^ Cuevas, Mayra; Sidner, Sara; Simon, Darran (February 24, 2017). "Dakota Access Pipeline protest site is cleared". CNN. Retrieved March 1, 2017.
- ^ Caraher, William R.; Weber, Bret; Kourelis, Kostis; Rothaus, Richard (June 1, 2017). "The North Dakota Man Camp Project: The Archaeology of Home in the Bakken Oil Fields". Historical Archaeology. 51 (2): 267–287. doi:10.1007/s41636-017-0020-8. ISSN 2328-1103.
- ^ a b Renshaw, Jarrett (April 19, 2017). "East Coast refiner shuns Bakken delivery as Dakota Access Pipeline starts". Reuters . Retrieved May 11, 2017.
- ^ Cama, Timothy (June 1, 2017). "Dakota Access pipeline now in service". The Hill . Retrieved June 1, 2017.
- ^ "Dakota Access pipeline starts transporting oil to customers". New York Daily News. Associated Press. June 1, 2017. Retrieved June 10, 2017.
- ^ McCown, Brigham A. (June 4, 2018). "What Ever Happened To The Dakota Access Pipeline?". Forbes . Retrieved June 7, 2018.
- ^ "More oil shipped as Dakota Access Pipeline expansion starts". AP News. August 6, 2021. Retrieved June 23, 2022.
- ^ Kearney, Laila (November 12, 2020). "Future of Dakota Access pipeline uncertain as Biden presidency looms". Reuters. Retrieved June 23, 2022.
- ^ Friedman, Lisa (March 25, 2020). "Standing Rock Sioux Tribe Wins a Victory in Dakota Access Pipeline Case". The New York Times . Retrieved March 27, 2020.
- ^ Fortin, Jacey; Friedman, Lisa (July 6, 2020). "Dakota Access Pipeline to Shut Down Pending Review, Federal Judge Rules". The New York Times . Retrieved July 6, 2020.
- ^ Associated Press (July 7, 2020). "Judge suspends Dakota Access pipeline over environmental concerns". The Guardian.
- ^ Frazin, Rachel (August 5, 2020). "Court cancels shutdown of Dakota Access Pipeline". The Hill . Retrieved August 6, 2020.
- ^ a b c d e f "Dakota Access Pipeline Facts". Dakota Access, LLC.
- ^ a b Petroski, William (August 25, 2014). "Should farmers make way for the Bakken pipeline?". Iowa City Press-Citizen.
- ^ Associated Press (July 7, 2020). "Judge suspends Dakota Access pipeline over environmental concerns". The Guardian.
- ^ "Energy Transfer LP (ET) Q2 2021 Results - Earnings Call Transcript | Seeking Alpha". seekingalpha.com . Retrieved August 26, 2021.
- ^ a b Petroski, William (February 9, 2016). "296 Iowa landowners decline Bakken pipeline". Des Moines Register . Retrieved November 6, 2016.
- ^ Petroski, William (July 7, 2014). "Bakken oil trains run through Iowa". The Des Moines Register . Retrieved December 4, 2016.
- ^ "Illinois oil train derailment involved safer tank cars". gmtoday.com. Associated Press. March 6, 2015. Retrieved December 4, 2016.
As of June of last year, BNSF was hauling 32 Bakken oil trains per week through the surrounding Jo Daviess County, according to information disclosed to Illinois emergency officials. ... According to the Association of American Railroads, oil shipments by rail jumped from 9,500 carloads in 2008 to 500,000 in 2014, driven by a boom in the Bakken oil patch of North Dakota and Montana, where pipeline limitations force 70 percent of the crude to move by rail.
- ^ a b "Energy Transfer: BAKKEN". Energy Transfer. Archived from the original on December 20, 2018. Retrieved February 3, 2019.
- ^ MacMillan, Hugh (May 12, 2017). ""Who's Banking on DAPL" Dakota Access Pipeline Finance Update". Last Real Indians.
- ^ "Who's Investing in the Dakota Access Pipeline? Meet the Banks Financing Attacks on Protesters". Democracy Now!. September 6, 2016.
- ^ "Norway's biggest bank may reconsider Dakota Access funding". CBC News. November 8, 2016.
- ^ Geiger, Julianne (November 7, 2016). "Another Setback For DAPL As Norwegian Bank Rethinks Funding". OilPrice . Retrieved November 8, 2016.
- ^ Chappell, Bill (February 8, 2017). "2 Cities To Pull More Than $3 Billion From Wells Fargo Over Dakota Access Pipeline". 2 Cities To Pull More Than $3 Billion From Wells Fargo Over Dakota Access Pipeline
- ^ "ING has sold its stake in Dakota Access pipeline loan" (Press release). ING Bank. March 21, 2017. Retrieved June 10, 2017.
- ^ Wong, Julia Carrie (March 21, 2017). "Dakota Access pipeline: ING sells stake in major victory for divestment push". The Guardian . Retrieved June 10, 2017.
- ^ "Why banks need to plug gaps in the Equator Principles to prevent community conflict | Reuters Events | Sustainable Business".
- ^ "Webinar: Equator Principles IV: A Human Rights Perspective".
- ^ Tchekmedyian, Alene; Etehad, Melissa (November 1, 2016). "2 years of opposition, 1,172 miles of pipe, 1.3 million Facebook check-ins. The numbers to know about the Standing Rock protests". Los Angeles Times . Retrieved December 3, 2016.
- ^ Yardley, William (November 9, 2016). "There's a reason few even knew the Dakota Access pipeline was being built". Los Angeles Times . Retrieved June 23, 2022.
- ^ Nowatzki, Mike (August 30, 2014). "'Stealth' North Dakota Bakken oil pipeline project faces fight". Pioneer Press . Retrieved December 4, 2014.
- ^ Aisch, Gregor; Lai, K.K. Rebecca (November 1, 2016). "The Conflicts Along 1,172 Miles of the Dakota Access Pipeline". The New York Times . Retrieved March 17, 2017.
- ^ a b Dalrymple, Amy (August 18, 2016). "Pipeline route plan first called for crossing north of Bismarck". The Bismarck Tribune. Archived from the original on November 1, 2016. Retrieved March 17, 2017.
- ^ "FAQ's". U.S. Army Corps of Engineers . Retrieved March 27, 2020.
- ^ a b c Thorbeck, Catherine (November 3, 2016). "Why a Previously Proposed Route for the Dakota Access Pipeline Was Rejected". ABC News . Retrieved March 17, 2017.
- ^ a b MacPherson, James (November 3, 2016). "If Dakota Access pipeline were to move, where?". Associated Press. Retrieved November 27, 2016.
- ^ Evans, Bo (August 18, 2016). "ND PSC says Dakota Access Pipeline will not come into physical contact with Missouri River". KFYR TV. Retrieved November 27, 2016.
- ^ Dakota Access Pipeline. Environmental assessment: Dakota Access Pipeline Project, crossings of flowage easements and federal lands (Report). U.S. Army Corps of Engineers, Omaha District. p. 385. Retrieved November 27, 2016.
- ^ Connie Sieh Groop (September 15, 2014). "Bakken pipeline would cross northeastern South Dakota to get to Illinois". Aberdeen News. Schurz Communications. Retrieved December 4, 2014.
- ^ Wan, Justin (December 22, 2016). "Dakota Access pipeline attracts protests as work nears finish line". Sioux City Journal . Retrieved October 1, 2019.
- ^ Hytrek, Nick (November 10, 2015). "Iowa board to receive public comment on proposed oil pipeline". Sioux City Journal . Retrieved October 1, 2019.
- ^ "Dakota Access Pipeline". Harvard Enviroenmental and Energy Law Program. October 24, 2017. Retrieved June 23, 2022.
- ^ "Live updates from Dakota Access Pipeline protests: 'It will be a battle here'". The Seattle Times. October 26, 2016. Retrieved October 26, 2016.
- ^ Sherman, Erik (June 14, 2017). "Court Sends Dakota Pipeline Back To The Environmental Drawing Board". Forbes . Retrieved July 19, 2017.
- ^ Beitsch, Rebecca (March 25, 2020). "Court sides with tribes in Dakota Access Pipeline case, ordering full environmental review".
- ^ Petroski, William (July 10, 2014). "Oil pipeline across Iowa proposed". Des Moines Register. Gannett Company. Archived from the original on December 4, 2014. Retrieved December 4, 2014.
- ^ Raffensperger, Carolyn (December 5, 2014). "A Legal and Political Analysis of the Proposed Bakken Oil Pipeline in Iowa". SEHN. Archived from the original on November 10, 2016. Retrieved February 2, 2015.
- ^ a b Dawson, Chester; Maher, Kris (October 12, 2016). "Fight Over Dakota Access Pipeline Intensifies; Company behind the project expects final approval; opponents vow to continue effort". The Wall Street Journal . Retrieved November 15, 2016.
- ^ Januchowski-Hartley, Stephanie; Hilborn, Anne; Crocker, Katherine C.; Murphy, Asia. "Scientists stand with Standing Rock". Science. No. 6307. p. 1506. Retrieved November 19, 2016.
- ^ Januchowski-Hartley, Stephanie (September 2016). "DAPL Scientist Sign-On Letter" (PDF). srjanuchowski-hartley.com. self-published. Retrieved November 14, 2016.
- ^ "Standing Rock Sioux take action to protect culture and environment from massive crude oil pipeline". Earth Justice. August 1, 2016. Retrieved November 15, 2016.
- ^ Lloyd, Jon (November 15, 2014). "Pipeline meeting to take place next month in Boone". Boone News Republican. Stephens Media LLC. Archived from the original on January 12, 2015. Retrieved December 4, 2014.
- ^ "Dakota Access Pipeline Project U.S. Fish And Wildlife Service Environmental Assessment Grassland And Wetland Easement Crossing" (PDF). U.S. Fish And Wildlife Service. December 2015. Retrieved February 24, 2015.
- ^ "August 2016: Iowa Progress Report" (PDF). Dakota Access, LLC. August 9, 2016. Archived from the original (PDF) on October 28, 2016. Retrieved November 15, 2016.
- ^ Archambault II, Dave (August 15, 2016). "Call to Action of Indigenous People's". Standing Rock Sioux Tribe . Retrieved November 15, 2016 – via Stand with Standing Rock.
- ^ Worldand, Justin (October 28, 2016). "What to Know About the Dakota Access Pipeline Protests". Time. Retrieved June 6, 2022.
- ^ a b Thorbecke, Catherine (November 4, 2016). "Why Previously Proposed Route for Dakota Access Pipeline Was Rejected". ABC News . Retrieved November 6, 2016.
- ^ "Three Affiliated Tribes issues support for pipeline protest". Associated Press. August 23, 2016. Retrieved June 6, 2022.
- ^ "Chairman Fox Conveys Extreme Adverse Impacts of Pipeline Closure on the Mandan, Hidatsa and Arikara Nation". Native Business. May 6, 2021. Retrieved June 6, 2022.
- ^ Petroski, William (March 16, 2015). "Meskwaki tribe opposes Bakken oil pipeline through Iowa". USA Today . Retrieved April 8, 2015.
- ^ a b Amundson, Barry (July 29, 2016). "Standing Rock tribe sues over Dakota Access pipeline permits". Grand Forks Herald . Retrieved August 6, 2016.
- ^ Kennedy, Merrit (September 9, 2016). "Judge Rules That Construction Can Proceed On Dakota Access Pipeline". NPR . Retrieved January 8, 2017.
- ^ Medina, Daniel A. (September 20, 2016). "Standing Rock Sioux Takes Pipeline Fight to UN Human Rights Council in Geneva". NBC News . Retrieved October 26, 2016.
- ^ Germanos, Andrea (September 25, 2016). "UN Experts to United States: Stop DAPL Now". Common Dreams. Retrieved September 27, 2016.
- ^ Medina, Daniel A. (September 13, 2016). "Sioux's Concerns Over Pipeline Impact on Water Supply 'Unfounded,' Company Says". NBC News . Retrieved December 3, 2016.
- ^ "CEO behind Dakota Access to protesters: 'We're building the pipeline'". PBS Newshour. November 16, 2016. Retrieved November 22, 2016.
- ^ Restuccia, Andrew; Palmer, Anna (December 16, 2016). "Trump team reaches out to Native Americans". Politico . Retrieved April 29, 2017.
- ^ a b c d "DAPL is the biggest issue in Public Archaeology right now". Master of Arts in Public Archaeology at Binghamton University. September 9, 2016. Retrieved May 9, 2017.
- ^ a b Jeff, Joeckel (November 28, 2001). "Introduction: Guidelines for Evaluating and Documenting Traditional Cultural Properties". National Register of Historic Places Bulletin (38). Retrieved May 9, 2017.
- ^ "National Historic Preservation Act, 1966 as Amended (2000)". Federal Emergency Management Agency. Retrieved May 9, 2017.
- ^ a b c d e f g h i j k Colwell, Chip. "How the archaeological review behind the Dakota Access Pipeline went wrong". The Conversation . Retrieved May 9, 2017.
- ^ "Pipeline Will Proceed Despite Tribal Protests". Courthouse News Service. September 9, 2016. Archived from the original on June 19, 2017. Retrieved May 9, 2017.
- ^ a b c d Nelson, Reid J. (May 19, 2016). "Ex-32-ACHP-Objection-Letter-DAPL". www.documentcloud.org . Retrieved May 9, 2017.
- ^ a b c "Grave Matters in Pipeline Controversy". WhoWhatWhy. September 19, 2016. Retrieved May 9, 2017.
- ^ a b "Did the Dakota Access Pipeline Company Deliberately Destroy Sacred Sioux Burial Sites?". Democracy Now!. September 6, 2016. Retrieved May 9, 2017.
- ^ a b c "State-Commissioned Archaeological Study Denies Standing Rock Experts a Voice". Indian Country Today. October 6, 2016. Retrieved May 9, 2017.
- ^ a b Ryzik, Melena (September 21, 2016). "Museum Officials and Archaeologists Sign Petition Against N. Dakota Pipeline". The New York Times. ISSN 0362-4331. Retrieved May 9, 2017.
- ^ Gifford-Gonzalez, Diane (September 13, 2016). "DAPL Letter" (PDF). Society for American Archaeology. Retrieved May 9, 2017.
- ^ Mufson, Steven (November 23, 2016). "Trump dumped his stock in Dakota Access pipeline owner over the summer". The Washington Post . Retrieved November 26, 2016.
- ^ "Trump's stock in Dakota Access pipeline raises concerns". Al Jazeera. November 25, 2016. Retrieved November 26, 2016.
- ^ "Million-Dollar Donors in the 2016 Presidential Race". The New York Times. February 9, 2016. Retrieved September 10, 2016.
- ^ Hampton, Liz; Volcovici, Valerie (November 25, 2016). "Top executive behind Dakota Access has donated more than $100,000 to Trump". Reuters . Retrieved November 26, 2016.
- ^ Milman, Oliver (October 26, 2016). "Dakota Access pipeline company and Donald Trump have close financial ties". The Guardian . Retrieved November 2, 2016.
- ^ "People at the front lines of the battle over the Dakota Access Pipeline are calling it a 'death sentence'". Business Insider . Retrieved March 3, 2017.
- ^ "#NoDAPL: Land Defenders Disrupt Gubernatorial Debate, Shut Down 5 Construction Sites". Democracy Now!. October 4, 2016.
- ^ "Life in the Native American oil protest camps". BBC News. September 2, 2016.
- ^ Bravebull Allard, LaDonna (September 3, 2016). "Why the Founder of Standing Rock Sioux Camp Can't Forget the Whitestone Massacre". Yes! Magazine. Retrieved October 25, 2016.
- ^ Liu, Louise (September 13, 2016). "Thousands of protesters are gathering in North Dakota – and it could lead to 'nationwide reform'". Business Insider . Retrieved September 20, 2016.
- ^ Gray, Jim (September 8, 2016). "Standing Rock: The Biggest Story That No One's Covering". Indian Country Today Media Network . Retrieved October 25, 2016.
- ^ "VIDEO: Dakota Access Pipeline Company Attacks Native American Protesters with Dogs and Pepper Spray". Democracy Now! . Retrieved November 6, 2016.
- ^ McCauley, Lauren (September 5, 2016). "'Is That Not Genocide?' Pipeline Co. Bulldozing Burial Sites Prompts Emergency Motion". Common Dreams.
- ^ Staff, ICTMN (September 4, 2016). "What Dakota Access Destroyed: Standing Rock Former Historic Preservation Officer Explains What Was Lost [Video]". Indian Country Today Media Network . Retrieved October 25, 2016.
- ^ Manning, Sarah Sunshine (September 4, 2016). "'And Then the Dogs Came': Dakota Access Gets Violent, Destroys Graves, Sacred Sites". Indian Country Today Media Network.com. Archived from the original on December 13, 2016. Retrieved September 6, 2016.
- ^ Silva, Daniella (October 27, 2016). "Dakota Access Pipeline: More Than 100 Arrested as Protesters Ousted From Camp". NBC News . Retrieved October 28, 2016.
- ^ "Developing: 100+ Militarized Police Raiding #NoDAPL Resistance Camp Blocking Pipeline's Path". Democracy Now!. October 27, 2016. Retrieved November 2, 2016.
- ^ Petroski, William (August 1, 2016). "Nearly $1 million in arson reported on Bakken pipeline project". Des Moines Register.
- ^ Aguirre, Joey (October 17, 2016). "Dakota Access offers $100,000 for information leading to arson conviction". Des Moines Register.
External links [edit]
- Dakota Access Pipeline - Official Website - Energy Transfer
- Dakota Access Pipeline - Project Maps - Energy Transfer
- Frequently Asked Questions DAPL US Army Corps of Engineers, Omaha Division
- SRS Tribal Council Meeting (Sept. 2014) audio. Standing Rock Sioux Tribe meeting with DAPL representatives
- Combined application of Dakota Access LLC for a Waiver or Reduction of Procedures and Time Schedules and for a Corridor Certificate and Route Permit Dakota Access, LLC (Dec. 2014)
- Map of Oil and Natural Gas Pipelines in the United States (Sept. 2015) - Pipeline and Hazardous Materials Safety Administration
- Memorandum Opinion of "Standing Rock Sioux Tribe vs U.S. Army Corps of Engineers" (Sept. 2016) - United States District Court
- Environmental assessment: Dakota Access Pipeline Project, crossings of flowage easements and federal lands Dakota Access, LLC; US Army Corps of Engineers, Omaha Division
- Chronology of Opposition to Dakota Access Pipeline from Standing Rock Sioux Tribe
olivarezinesepark.blogspot.com
Source: https://en.wikipedia.org/wiki/Dakota_Access_Pipeline
0 Response to "Are They Going to Continue the Dakoto Pipeline Are They Going to Continue the Dakota Pipeline"
Kommentar veröffentlichen